Overview


The purpose of Parts Per Hour is to calculate and display the an ongoing target for good parts based on the operation time.  Using operation times, it is possible to display the expected parts per hour for a specific part and machine combination.  To start, operation times need be assigned to the machine and part combination.  To do this follow this link to understand how to setup operation times.  More Information 



Part Per Hour Metrics Defined


Parts Per Hour

PPH - This is the expected parts per hour.  For instance, if an ideal cycle time of 10 minutes, then this number would be 6 PPH. 

Parts Per Hour Plan

PPH plan - The amount of parts that should have been made already based on the ideal time, the current time, and the start time for this calculation.  If a work order is active, the start time will be when the work order started. If a work order is not active, then the  start time will be the last shift change.  If shifts are not defined the start time is midnight.  

Parts Per Hour Actual

PPH Actual - The current parts made since the start time.

Parts Per Hour %

PPH % - The percentage of parts currently produced to the Parts Per Hour Plan. [PPH % = Good Parts / PPH Plan] 



Part Per Hour Calculation


Planned downtime can be excluded from the PPH calculation, and it is possible to control which planned downtimes are used in the parts per hour calculation.  This is done under the Manage tab, metrics, and Metric Definitions.  If any changes are made to the Planned Downtime settings, all data going forward will reflect those changes.  Within the RTV screen, the Parts Per Hour metrics reset at the start or end of a new part, the start or end of a shift, or if a shift is defined but has not started within the past 24 hours it will reset the Part Per Hour count at midnight.  When using the historical PPH report here, the PPH numbers are determined by the operation time defined by that machine and part combination over the selected time period. 




Example Screen shot of Parts Per Hour in the RTV Grid


Each of the following columns can be enabled or disabled in the RTV Equipment Status Grid.